Description
The project comprises measures to improve the quality and management of drinking water as well as the collection and treatment of wastewater in the City of Gdansk, Poland in order to comply with EC Directives.
Objectives
The investments fall under the capital program for the years 2010-2014, which is driven by the need to renew and extend the existing asset base, raise efficiency, secure supply and service to customers as well as increase drinking water quality and comply with EU Directives.
Scope of work
Water supply network
New network - c.a. 13,0 km,
Pressure rising station - 1.
Sanitary network
New network - c.a. 27 km
Reconstructions of the network (gravitational & pressurized) - c.a. 4,5 km
New waste water pumping stations - 10.
Demolition of waste water pumping stations - 3.
Modernization of waste water pumping stations - 2.
Sludge disposal
Energy Recovery Installation (CHP)- 1.
Sludge Incineration System (ITPO) - 1.
Tasks
Tasks related to water supply network
Water supply network and retention tank to connect Sobieszewska Island to Gdansk Water supply system together with construction of water supply system Water supply network for stadium
Tasks related to water supply and sanitary network
"Construction of sanitary and water supply networks in the Osowa district"
Tasks related to sanitary network
- Construction of waste water pumping station at Pomorska St together with reconstruction of sanitary network at Jelitkowska
- Sanitary Collector WM-1 "Nowa Wałowa" from Kliniczna St. node to Ołowianka Pumping Station
- Construction of sanitary and water supply network in the Maćkowy , Osowa Smegorzyno district
- Reconstruction of sanitary network in the discharge area of Waste Water Pumping Station "Czerwony Most
- Modernization of Załogowa waste water pumping station
- Construction of sanitary and water supply network for Euro 2012 PGE Arena Gdansk at Gdansk Letnica
Tasks related to the sludge disposal
Extension of "Gdansk East" WWTP - stage II b - sludge disposal Construction of waste water pumping station "Kochanowskiego"
Total cost
Up to PLN 293 million (ca. EUR 75 million). The project is to be financed by The European Union up to 56 % of qualified expenses.
Realization
The project completion date is 31.12.2014.